LATEST NEWS

January 2008

The Mall Corporation - Maidstone

The new 19XR5050 chiller has now been running without problem since early 2007 and has now reached An approximate run time of 3100 Hrs (Jan 2008). Addition work to the BMS and Control systems has now refined the condenser water temperature, cooling tower operation and chilled water distribution allowing additional operational savings to be made by the client.

Click photos to enlarge


Chiller Replacement Work - Wells Street - London - W1

Chillmech Engineering Staff have successfully replaced a 'York' YCWA 5HE 180 Air Cooled Liquid Chiller located at roof level of a commercial office complex in 'Wells Street' ( Oxford Street ) London W1.

The existing York Chiller was installed in 1994 and provided approximately 630 Kw of cooling to various fan coil units and Air Handling Units within the Building.

Two new 'Carrier' 30RB342 'Aqua Snap' Air Cooled ( Multi Scroll Compressor ) Chillers were selected to replace the 'York' Chiller with. Each of the new units has a Nominal Cooling Capacity of approximately 325 Kw.

Click photos to enlarge

Work was undertaken during the winter period to minimum disruption and discomfort to staff within the building. In order to meet stringent noise levels in this area of London the New Chillers were provided with 'Inverter' Control of all condenser fan motors and all compressors have been enclosed within acoustic housings. The new Chillers now provide the efficient and economical usage required by the client while minimising the noise output.

Approx value of work undertaken: £120,000

Commissioned: April 2006 and handed over after 1st Year to client in May 2007.


Chiller Replacement Work - Southampton Marina

Frequent failures and expensive repair bills on existing 'Trane' LCGAE 207 Air Cooled chillers located at a prestigious office complex in the 'Ocean Village' area of Southampton Marina called for swift replacement work to be carried out. Click photos to enlarge

Click photos to enlarge

Within a very short time our Engineers De-commissioned both of the Trane CGEA Chillers ( approx 160 Kw each ) and replaced them with 2 x Carrier 30RA160 'Aquasnap' Air Cooled Chillers. Each providing 167 Kw of Cooling to the building. The Majority of the replacement and cranage work undertaken during just one weekend with final commissioning taking place just 4 days after.

The roof area on this site was particularly confined and the introduction of the new 30RA Chillers enabled additional service and air space around the equipment to allow on-going maintenance and upkeep of the Chillers. The ultra quiet and efficient 'Flying Bird' condenser fans on the new chillers also helps to push the heat rejected from the equipment out through the roof support gridwork

Additional work was required to replace DX cooling circuits to the 'Fresh Air' Air Handling unit and various other Split Systems was also undertaken at the same time to enhance the entire building.

Commissioned: August 2006

Project Value: Approx £ 117,000


Mascalls School - Paddock Wood - Kent

A new 'Art Exhibition Centre' has recently opened to the public within the Mascall's School Grounds. The new Art Centre is built on the site of the old school music room which was demolished to make way for this purpose built accommodation for an ever increasing array of art exhibitions.

Many of the Art Exhibitions require that the room is conditioned to provide a constant minimum temperature of 20 oC and a Humidity level of approx 50% RH. To meet these general demands Chillmech Limited installed a 'Trane' WSH 060 Rooftop Package 'Heat Pump' complete with all necessary insulated ductwork, internal air grilles and fresh air intake. Click photos to enlarge

Click photos to enlarge

An internally mounted electronic temperature / time controller is responsible for maintaining a steady room temperature 24/7 and the adjustable 'Fresh Air' intake helps to maintain a fairly steady humidity level.

The new Package system is capable of approx 20 Kw of summer cooling to the Building via four ceiling mounted diffuser grilles. Heating for the Winter period is provided via ' Reverse Cycle' Heat Pump operation and this enables up to 21 Kw of heat to be introduced.

Obviously the new system needed to be as quiet as possible and noise was reduced to a minimum by using larger than necessary supply air ductwork and air supply grilles. The return air is recovered from low level within the exhibition Centre and returned back to the roof package unit by using internal bulkheads and void spaces. The system works very peacefully.

Local media attention pulled in more than 3,500 visitors during the first three exhibitions including many educational visits from across the region. The gallery visitor's book is now brimming with compliments describing Mascalls Gallery as "Paddock Wood's little gem", "full of visual wonders" and curating exhibitions of "stunning work".

Total cost of all A/C and Ventilationwork: Approx £ 18,000

Commissioned during: September 2006


The Royal National Theatre - Southbank - London

As part of an on going replacement and energy saving drive by the Royal National Theatre, an Existing 1976 'Carlyle' Air Handling Unit serving the 'Front of House' area has recently been replaced with a new ECE modular 'Inverter' Controlled Air Handling Unit. Click photos to enlarge

Click photos to enlarge

The new AHU was specifically designed to accommodate a new type of 'Adiabatic' Type Humidifier which is being tested as a low energy alternative solution in place of previous 'Steam Type' ( Vapac ) - electrode steam generators. Initial results for the Humidifier section alone have shown that the electrical savings made between July and December 2007 are a fraction of the normal cost.

An equally sized steam humidifier would have operated at approximately 30 Kw power consumption on full load wheras the adiabatic equivalent requires only 900 watts ( at full load ) of electrical consumption. The only small drawback is that the new humidifier requires much more water flow to maintain the correct humidity and frequent cleaning of the wetted filter pads and drain tray.

Chillmech Limited worked closely alongside 'Walter Meier Ltd' ( Axair Climate Ltd ) engineers on this project to enable the fitting of their 'Condair' SH2 Adiabatic Humidifier unit. The Fitting and Control of the new system was made efficiently and quickly, the system is now connected to the RNT BMS 'Trend' System and allows 10% to 100% of humidity control to be maintained.

The new AHU Commissioned during July 2007.

Total Value of this project approx: £48k


Swansea - Vrv System

Chillmech Engineering staff have installed and commissioned a new 'Daikin' VRV111 ( Variable Refrigerant Volume ) 'Heat Pump' Comfort Cooling system into a commercial building in Swansea - Wales. The installation will help to combat the very high temperatures experienced within the building between May and September each year and also to provide a more economical heating system for the winter period.

The building was previously heated by individual wall mounted electric panel heaters which were extremely inefficient and costly to run. The new system only uses a third of the electrical power to provide the maximum heat needed. Suffice to say all wall mounted electric heaters have now been removed. Click photos to enlarge

Click photos to enlarge

The installation of the new A/C was made even more complicated in that all services had to be surface run inside trunking which therefore involved nearly all 'Out of Hours' working so that none of the office staff were prevented from undertaking their 'Day to day' business.

The completed system comprises of a Daikin RXYQ8P and RXYQ10P size outdoor condensing unit which are connected to approx 26 various size indoor units.

A remotely adjustable DCS601 Intelligent Touch Controller is installed to provide full control to the equipment. The system is monitored via BMS open protocol software from the clients Head Office in London.

Total value of all work: Approx £ 90k

Commissioned during Late 2006.


The Mall Corporation - Maidstone

February 2006

As part of a continuing refurbishment and replacement schedule for the Shopping Centre Management, Chillmech Limited have replaced one of the original ( 1976 ) Carrier 19EA8583DN ( R12 ) Centrifugal Liquid Chillers located in the Main Plant Room with a new generation 19XR5050 Carrier centrifugal chiller which uses an environmentally acceptable R134a refrigerant. The original chillers have been operating and very reliable since commissioning in 1976 but they rapidly approach the end of their useful working life.

The Centre Relies on a constant supply of Chilled water to the Mall Areas, shops and offices to maintain the working environment. During peak summer ambient temperatures a total cooling demand of approximately 3000 Kw is required to maintain conditions within the Centre. The replacement work has been completed ahead of the 2006 summer season so that cooling can be relied on by the Shoppers and Management of the Centre during the forthcoming warmer months.

One of the hardest tasks during the replacement work was removing the old cooler/condenser shell of the original 19EA chiller from within the plant room. This weighs approx 7.5 Tons and eventually had to be cut up on site before transporting the sections through the loading bay doors.

The new chiller is expected to be more efficient than the original chiller and Chillmech 'On Site' Engineers will be closely monitoring electrical consumption for the new machine in 2006 to enable us to identify actual cost savings to the client. A short delay in delivery of the chiller to site was created by the specialist 3.3Kva ( 3300 volt ) motor which runs the compressor section as this had to be specially made by 'Carrier' at their US manufacting plant.

Total Value of work approx £ 250k


Chillmech Ltd have been succesful at winning a significant contract at 'The Department for Education and Skills' in Westminster - London. During August 2005.

The contract involved the planned replacement of all 'Service Pumps' within the basement levels of the building and was undertaken over a period of 16 weeks and finally completed ahead of schedule at the end of December 2005.

Work involved replacement of heating Pumps, Sump Pumps and Booster Sets within the basement plant rooms and the Project needed to be undertaken without any disruption to the building. The Booster sets were purpose made by Manufacturer 'New Haden Pumps Limited' and all three replaced over just one weekend which included the entire replacement of all electrical cables, pipework connections and pressure vessels. Water Services were restored to the building before 5pm on Sunday evening.

The total value of all work carried out exceeding £250k

December 2005

 


November 19th 2005 saw Three Carrier 30RA240 air cooled liquid chillers being lifted onto the roof of a PWC Plc Building in Farringdon Street - London.

The installation involved the removal of three existing YORK AWHP 90 Heat Pumps, all associated pipework and electrical services before the new chillers were able to be positioned onto the prepared bases and piped up to the existing chilled water headers.

Each of the new chillers will provide a nominal cooling duty of approx 252 Kw for cooling the 7 heavily occupied floors of this building. This work completes a 3 year structured replacement of all chillers in the building which now totals NINE x 30RA240 chillers in all at a total cost of around £500k

The client has been very happy with the new chillers and their ability to control the leaving chilled water at 7 oC has made the performance of the other equipment in the building far more efficient. Reliability of the new 'Carrier' equipment has seen only one problem within the last three years ! and this has been a failed condenser fan motor, which was quickly replaced under warranty by 'Carrier Ltd'.

November 2005.


Chillmech's Engineering team are responsible for ongoing project work for replacement of some of the older 'Carlyle' Air Handling units at the Royal National Theatre - Southbank - London.

Recent work has involved the removal of a ( 1976 Year ) Carlyle Air Handling unit from one of the internal Plant Room Areas. The work could only be undertaken during nightime and weekend periods to minimise any noise disturbance to Matinee or Rehearsal Performances within the Theatre Areas of the Building. Once the old unit had been removed in sections by our engineers it was replaced with a new ECE modular System which included inverter motor control, Humidifier unit, cooling and heating sections.

The new Air Handling unit has vastly improved air quality to one of the larger Rehearsal Rooms and along with several ductwork revisions has now also improved air distribution within the same area. The new system enables the best possible use of 'Free Cooling' by using outside fresh air to the room before any cooling is provided by mechanical means.

September 2005


Trade Press Release for new 'Carrier' 30HXC260 chillers installed in Department for Education and Skills - Westminster - London

Date of Installation: May 2004 through to September 2004

MEDIA: H + V News - 23rd April 2005

Value of work: £ 441,000.00

Editorial Reads

Installing four 'Carrier' Global chillers in a B2 level basement plant room with only a standard doorway for access called for what Michael White, Managing Director of Chillmech Limited, describes as "keyhole surgery"!

When the original R22 reciprocating chillers were installed in the basement of Sanctuary Buildings, around 20 years ago the plant room was built around them. Replacing them involved complex and careful planning to ensure that the 8-storey building, home to the Department for Education and Skills, was never without cooling during the working week. It was also important that noise levels were kept to a minimum so as not to disturb ministerial meetings that take place in the building.

"And that's where the keyhole surgery came in" says Chillmech's MD Michael White.

To allow access, a hole measuring 1.5m2, the largest possible because of surrounding obstacles, was cut into the plant room wall. The original chillers were then dismantled one by one and together with associated piping were removed through the hole. The floor surface in the plant room was then prepared and the first two Carrier units, each measuring 3.9m long, 2.1m high and 1 metre wide were taken in piece by piece and reassembled within the plant room, together with chilled water pipe work, electrical services and a BMS interface module. After these first units were installed and commissioned, the exercise was repeated with the second pair of chillers.

The new chillers supply chilled water to 1320 fan coil units within the building and rooftop air handling plants to maintain comfort for the 1800 people working within the building.
April 2005


Two chillers installed at the
ITN Headquarters building in
London

Dec 2003

h&v news, October 25th 2003


Carrier Dealer of the Year
announced at
2003 UK Sales Conference


March 2003

Michael White, Director and Co-owner of Chillmech Limited received the prestigious accolade of Carrier Air Conditioning Dealer of the Year 2002-3, at this year's Carrier Dealer Conference, held recently at a medieval manor near Stratford on Avon. The Award was presented by David Appel Managing Director of Toshiba Carrier UK Ltd.

Following the Award for his company's record sales of Carrier equipment Michael entered into the spirit of the event by accepting his nomination as 'King for the day' and then presided over an entertaining medieval banquet -during which my lord Tyson was punished by the Master of Ceremonies for his truculent attitude!

Chillmech Limited who are based in Paddock Wood, Kent was founded in 1976, and bought by its current directors in 2000. It specialises in providing its clients with a comprehensive package for new or replacement Chillers and has undertaken installations directly for GlaxoSmithkline plc, Price Waterhouse plc, and ITN to name a few. Michael White said, "We have been growing steadily over the last four years and we are delighted to achieve this notable milestone."


The Carrier Pigeon
Issue 3 - 1999

"Chillmech supplies the full range of
Carrier equipment. Known as a
heavy equipment dealer, the
company specialises in higher
capacity centrifugal and large
water chiller projects"


SmithKline Beecham (SKB)
1998

BT Bletchley
Milton Keynes
1993

Home Page
Contact
Enquiry